B4001. Complete assembled underground piping system
Prices are based on a length of at least 10 km in a relatively open outside infrastructure.
Variation
Prices are strongly influenced by:
Depth;
Geography;
Soil type;
Number of road and water crossings;
Insulation;
Working pressure;
Agriculture and land situation;
Material prices.
Including:
Indirect costs (construction management), general overhead cost;
Design (pressure 60 bar, temperature 50 °C, no thermal insulation);
Compensation of land owners and land users;
Materials and erection;
Testing and commissioning;
Temporary building facilities;
Small road- and water crossings (2 drills of 400 meter each);
Ground cover 1.25 meter.
Excluding:
Big river-, channel- and road crossings;
PIG launcher, receiving station and block valves;
Licences and tax;
Owners internal costs.